Secretary Municipal Administration Arvind Kumar along with the Mayor B Rammohan
today visited Kukatpally and inspected the Balanagar flyover works.MLA M Krishnarao and local corporators were also
present.
Mr
Arvind Kumar asked the engineers to utilize the lockdown period to expedite the
foundation works and also take up construction of the retaining wall. As the land acquisition process is complete,
he asked the officials to speed up the civil works by instructing the
contractors to bring in more manpower and material.
HMDA
Chief Engineer B L N Reddy informed that as there is very less traffic owing to
the lockdown, seven foundations which could not be completed earlier due to road width constraints and properties acquisition
have now been completed. Another two
foundations will also be completed by the end of this month, he added.
Construction
of flyover between Balanagar crossroads to Narsapur cross roads was taken by
the HMDA. A 6 lane two way flyover in
the direction of Kukatpally Y junction to Bowenpally junction crossing Narsapur
cross roads and Fatehnagar junction was envisaged. The total cost of the project is Rs 387
crores of which Rs 265 crores is towards land acquisition while the remaining
122 crores is towards civil construction work.