Nala desilting works are taking place in city at a rapid
pace. GHMC has developed yearly schedule of Nala desilting works on
the instructions of Minister for MAUD Mr.K.T. Ramarao.An action plan is
prepared on desilting of nalas before and after rainy season.GHMC Mayor Bonthu
Rammohan has instructed concerned officials to take up desilting works by using
additional machinery keeping inview of ensuing rainy season, during lockdown
period.Mayor has inspected nala desilting works on 9th May that are taking
place in Shaikpet.
MAUD
Principal Secretary Mr Arvind Kumar has inspected Dabeerpura nala extension
works worth of Rs 2crore along with MLA Ahmed Pasha quadri. MLC Riyad ul
Hasan, Corporator Basith , Narsing Rao S.E., ,Deputy Commissioners
MangaTayaru, Suryakumar , Rajanikanth Reddy and others were also present
during the visit.
Speaking
to media GHMC Maintenance wing Chief Engineer Jiyauddin told that as part of
yearly schedule 4 lakh 79 thousand cubic metres silt is to be removed and 345
works have been sanctioned in this regard. During this season a target of 3
lakh 29 thousand cubic metres silt is proposed to be removed out of which 2
lakh 60 thousand cubic metres silt is removed so far.In another 10 days
targeted desilting works will be completed under the supervision of
concerned officials , he told.Removed silt is being shifted to Jawahar nagar
dumping yard , he added. In those areas where lanes are too narrow, desilted
material is shifted to identified dumping points and is later shifted to
Jawahar nagar yard.To speed up desilting works in Khairatabad and Secunderabad
areas more number of labour are engaged.90 percent desilting works are
completed in Charminar zone ,he said.He also said iron fencing is arranged
around big nalas as per the rules in practice.
-Press note